SAINT-ETIENNE – FURANIA (France)

Waste water treatment plant of 282 000 p.e. (maximal capacity) and 233 000 p.e. (rain periods)

FMI PROCESS exploits the thermal valorization of sludge process since June 2014. The contract has been renewed until September 2022 (8 years), then until june 2029 (6 years and 9 months).

Since 2020, more than 97% of sludge have been valorized on the FMI Process unit. The thermal energy produced is valorized by the anaerobic digester and the heating of the building to improve the biogas production.